Kansas City Missouri School District — Missouri DNR Asbestos Records
Kansas City Missouri School District in Jackson County County, Kansas City, MO has 8 documented asbestos project notifications on file with the Missouri Department of Natural Resources under the NESHAP program.
Documented asbestos-containing materials (ACM) include: duct insulation, gaskets/packing, pipe insulation.
These are public regulatory records of licensed asbestos abatement and demolition/renovation work conducted at district facilities. Each notification represents a separate project where asbestos was identified and removed by a licensed contractor.
If you or a family member worked at, attended, or was otherwise present at facilities operated by Kansas City Missouri School District and has been diagnosed with mesothelioma, asbestosis, or another asbestos-related disease, these records may be relevant to a legal claim.
Missouri DNR Asbestos Notification Records
The following 8 project notification(s) are documented with the Missouri Department of Natural Resources (NESHAP program) for Kansas City Missouri School District in Kansas City. These are public regulatory records.
| Project ID | Year | Site / Building | Operation | ACM Removed | Contractor |
|---|---|---|---|---|---|
| 462-97 | 1997 | 1997 O&M Three Trails School | Renovation | 160 sq. ft. ACM, 260 ln. ft. ACM 8(A-I) | Major Abatement & Demolition Inc. |
| 463-97 | 1997 | 1997 O&M Sugar Creek School | Renovation | 160 sq. ft. ACM, 260 ln. ft. ACM 8(A-I) | Major Abatement & Demolition Inc. |
| 521-97 | 1997 | 1997 O&M Van Horn High School | Renovation | 160 sq. ft. ACM, 260 ln. ft. ACM 8(A-I) | Major Abatement & Demolition Inc. |
| 1074-97 | 1997 | Three Trails Elementary School under ‘97 O&M | Renovation | 250 sq. ft. duct insulation 8(A), 400 ln. ft. pipe insulation 8(D-I) | Major Abatement & Demolition Inc. |
| 1182-97 | 1997 | Sugar Creek School under ‘97 O&M | Renovation | 400 ln. ft. pipe insulation and fittings 8(D-I) | Major Abatement & Demolition Inc. |
| 1202-97 | 1997 | Sugar Creek School under ‘97 O&M Project #3 | Renovation | 275 ln. ft. pipe insulation/fittings 8(D-I) | Major Abatement & Demolition Inc. |
| 1488-98 | 1998 | 1998 O&M Sugar Creek School | Renovation | 160 sq. ft. ACM, 260 ln. ft. ACM 8(A-I) | Major Abatement & Demolition Inc. |
| 1806-98 | 1998 | Van Horn High School Emergency Project | Renovation | 160+ sq. ft. ACM debris cleanup 8(A) | Major Abatement & Demolition Inc. |
Source: Missouri Department of Natural Resources, NESHAP Asbestos Abatement & Demolition/Renovation Notification Program — public regulatory records.
For informational purposes only. This page reproduces public regulatory data from the Missouri Department of Natural Resources. Contact a licensed attorney for legal advice.